Project name : National Afforestation project
Phase no. : 0
Country : CHINA

  General Site details Technical aspects Socio-economic aspects Institutional aspects   Results   Comments  
 

Results

 
     
 
Outputs, reports, publications(include access details or attach documents)
  Implementation Completion Report No. 18130, June 1998; Staff Appraisal Report No. 8487-CHA, May 1990 (containing list of Working papers and Document in the project file - Annex 7: p 80  
 
Rate the success of the project on a scale of 1-10 in the perspective of the respondent (0=unrated)
  0  
 
Did the project meet the objectives (or is it likely to)?
 
Main objective --
Specific objectives/targets --
Activities planned --
 
 
Other major unplanned outcomes
 
Positive Negative
-- --
 
 
Underlying reasons (could be technical, ecological, institutional, socio-economic, and could be project related or beyond) for outcomes:
 
Positive reasons Negative reasons
-- --
 
 
Recommendations
  --  
 
Major insights or lessons learned
  The borrower was in the driver seat; where institutional capacity is robust, an investment project can be treated as a program or sector loan; a project with highly focused investment objectives can nonetheless generate a broad sectoral impact; further sectoral policy reform is needed to complete the transition to a market economy; the project achieved a high impact from research that had already been done, but did not address the broader constraints affecting future research; the linkage of financial control with technical standards was critical to project success  
 
 
     
 
     