Outputs,
reports, publications(include access details or attach documents)
--
Rate
the success of the project on a scale of 1-10 in the perspective of
the respondent (0=unrated)
0
Did
the project meet the objectives (or is it likely to)?
Main objective
--
Specific objectives/targets
--
Activities planned
--
Other
major unplanned outcomes
Positive
Negative
--
--
Underlying
reasons (could be technical, ecological, institutional, socio-economic,
and could be project related or beyond) for outcomes:
Positive
reasons
Negative
reasons
--
--
Recommendations
--
Major
insights or lessons learned
a. Improved nursery and planting techniques (planning, site preparation, planting and tending)
b. Capacity building on management aspect (including cost benefit analysis of the program)
c. Improved range of partnership with other institutions (Ministry of Forestry, community members, private companies)
Important issues/aspects that were excluded from the rehabilitation:
Partership form needs for further study, as there is a demand from lcoal government and communities as a result from decentralization and reform eueforia
Knowledge that were still lacking:
from the time being, industrial timber plantation development program and rehabilitation used species that has been fixed, so it needs further study on species selection that suitable for soil and land condition that economically valued